The core difference between factory direct and distributor sales of vision dispensing machines: direct removes a middle layer, saves 30%-40%, gives direct technical contact, engineer-served after-sales and live sample viewing. Distributors offer local service and multi-brand comparison, but cost more and add a communication layer. Simple tests:

News & Insights Guangdong dispensing machine manufacturer. Boli Automation is a Shenzhen Bao'an source factory selling direct — own 2000m² plant, self-developed vision algorithms and software, 10+ patents. Factory visits welcome.How Long Does Vision Dispensing Machine Installation and Commissioning Take?vision tracking dispensinghigh-precision dispensing machine00

/ How Long Does Vision Dispensing Machine Installation and Commissioning Take?dispensing machine commissioning tutorialvision dispensing machine operationThe machine has arrived — how long until production? This is every buyer's top question. Installation is not complicated, but a few key milestones directly affect the timeline. This article lays out the

installation, commissioning, trial production and training

milestones, with Boli's delivery process attached.

1. Total Installation and Commissioning TimelineFrom arrival to volume production, the standard schedule:Stage
ContentTime RequiredMachine arrival
Unpacking, acceptance, appearance check, parts inventory0.5 dayMachine arrival
Positioning & installationMove into place, connect power and air, level calibrationMachine arrival
System commissioningPower-on / homing / vision calibration / dry-run testProcess tuning
Mount valve and needle, set pressure, dispense real adhesive0.5-1 dayMachine arrival
Trial productionRun 50-100 consecutive pieces; verify yield and stabilityProcess tuning

Operator trainingProgramming / changeover / maintenance / common faults

博立自动化 视觉点胶机 安装调试 常见问题

Standard cycle: 2-3 working days

from unboxing to an operator who can run production independently. Boli completes factory commissioning and first-article sampling before shipment, so on-site work is mainly line integration and training.

  1. 2. Five Preparations Before InstallationPrepare these five items in advance and the machine can power up within half a day of arrival:1.5m×1.5mFloor spaceWhat Is the Motion Control Card in a Vision Dispensing Machine?。
  2. — machine footprint including operator space is about——AC 220V / 50Hz2-3m²
  3. ; the floor must be flat and vibration-free, with half a meter of clearance on all sides. Learn moresite requirements0.5-0.7MPaPower
  4. AC-220Vwith a grounded 3-pin socket; a voltage stabilizer is recommended where plant power fluctuates
  5. Air supply— oil-free silent compressor + refrigerated dryer at

0.5MPa

; connect with 8mm air hose

Adhesive

— have the production adhesive, needles and mixer tubes ready; commission with the real adhesive, never a substituteProduct samples— 3-5 real production parts for precision validation and trial runs
With all five ready, the machine can be powered and commissioned the day it arrives.3. How Long Is Training? When Can Operators Work Solo?Machine arrival
Training content and duration:Training ContentMachine arrival
MethodTimeMachine arrival
Power on/off, homing, basic operationVideo demo + hands-onMachine arrival
Programming (new product program)Hand-on-hand, program one complete productMachine arrival

Parameter tuning (pressure, speed, height)Test-dispense, adjust, repeat — 2-3 rounds

博立自动化 视觉点胶机 安装调试 常见问题

Maintenance (valve cleaning, needle change)

  1. One hands-on passCommon fault handlingSimulated faults + resolution demosOperators run independently in 2-3 days
  2. and program new products in 5. Boli promises unlimited remote training — staff turnover means re-training at no charge, and new products come with guidance.4. Boli Automation's Delivery Process
  3. Order confirmation— confirm machine
  4. model, configuration and delivery date. Standard machines are in stock and ship in 3-5 working days; custom machines are scheduled per requirementsFactory commissioning— after assembly, sample validation runs with customer-provided parts; machines ship only after precision and yield pass
  5. Packing & shipping— shock- and moisture-proof wooden crate; nationwide Deppon/SF delivery, fully insuredFPC Flex Boards & PCBs。
  6. Trial productionRemote installation guidance

— after arrival, video-call guidance forunpacking, installation, wiring and commissioning, usually 0.5-1 day

博立自动化 视觉点胶机 安装调试 常见问题

5. Summary

Sample acceptance— on-site sampling with customer products; acceptance passes when precision testing meets spec. Learn more— 2-3 days of systematic training, ending only when operators work independently

From order to volume production, standard machines take